Cumberhead and Dalquhandy wind farm have agreed to a shared connection point, which will consist of shared 120MVA 132/33kV transformer at the new Cumberhead Collector substation which will be situated within the Dalquhandy Wind Farm boundary close to Stockhill Farm, near Coalburn.
• Excavation and construction of various concrete foundations.
• Excavation of trenches and installation of cable ducts and foul and surface water drainage.
• Supply and installation of cable trenches.
• Excavation and installation of below ground earthing.
• Construction and maintenance of roadways and perimeter footpath.
• Construction of palisade fence and gates.