The project involves the formation of new access junction at Balmore Road and Lochfaulds Road and new compound storage area for the Lochfaulds Solar Park.
𝗢𝘂𝗿 𝘀𝗰𝗼𝗽𝗲 𝗼𝗳 𝘄𝗼𝗿𝗸 𝗶𝗻𝗰𝗹𝘂𝗱𝗲𝗱:
𝗣𝗵𝗮𝘀𝗲 𝟭𝗕 (𝗦𝗼𝘂𝘁𝗵 𝗙𝗶𝗲𝗹𝗱):
• Construction of a new south access track
• Upgrades to east side access track
• Installation of new drainage under the access track
• Foundations for CCTV installations
• Duct crossing at Lochfauld Road
• Excavation and installation of various ducting works
𝗣𝗵𝗮𝘀𝗲 𝟮 (𝗖𝗲𝗻𝘁𝗿𝗮𝗹 & 𝗡𝗼𝗿𝘁𝗵 𝗙𝗶𝗲𝗹𝗱𝘀):
• Additional drainage south of the substation and north of the central hardstanding
• Foundations for CCTV and inverters
• Site fencing and installation of gates
• Breakout and granulation of the remainder of Lochfauld Road
• Installation of new culvert
• Excavation and installation of various ducting works