Project Description
The construction of two state-of-the-art maturation warehouses adjacent to the existing Glenglassaugh facility.
Warehouse 7, covering a footprint of 3,861m², and Warehouse 8, with 1,860m², are both designed with steel frames and equipped with advanced fire protection systems.
Works Included
- Construction of 2 new maturation warehouses
- Installation of composite roof and wall cladding
- Roof ridge venting
- Removal of 6,900m³ of topsoil
- 4,830m³ of cut and fill
- Vibro-compaction piles
- Installation of storm drainage, power, and water supply connections
- 3,752m² concrete access road and service yard